How do builder payment stages work?

The short answer

Madisons builds your house with your money, so Craig sets out the stages plainly. Once you have accepted a price, a 5% slot holding deposit secures your start date, even if that is months away. About two weeks before we start, a further 15% brings the deposit to 20%, which covers the site set up, preliminaries and management, and materials on site. For the first two or three weeks on site there are no further charges. After that, stage payments are agreed for your project, for example 20% on completion of the foundations. Ask about the stages for your own job when you talk to us about design and build.

Transcript

People tend to ask about payment stages. For us as a contractor, we build your house with your money, because at the end of the day, it’s your house.

So if we’ve got an agreed price, for instance, so you’ve given us drawings and engineering and all the rest of the bits and pieces that we need to be able to price a job, [inaudible] the price, you’re happy with the price, it meets your budget, but we’re not starting to build for another three, six months, a year, I don’t know, whichever that time frame is. We would take a slot holding deposit, which would be 5%, which secures your slot in that time frame, that timeline, which then puts a little bit of skin in the game for both of us. We’re securing a timeline, you’re putting money in to secure that timeline.

And then, prior to starting, we would take an extra 15%, which would be probably about two weeks before we start. So we’ve got a 20% deposit. In that deposit then, we then secure, if we need toilets and materials and skips, all that, the whole site set up, prelims and management, the structure, drawings in, getting stuff printed off, all that, materials on site.

And then we would work then, probably for the first two or three weeks, there wouldn’t be any charges, no extra charges. We’d agree the next stage, whichever that would be, maybe on completion of foundations, we would then invoice another 20%, or whatever stage payments we agree for that particular project, because that may be a bit more demanding, or there may be a bit longer, who knows? But stage payments would be set up.

Transcript lightly edited for reading: filler words and false starts removed. The captions on the film are word for word.